West Goshen Township

West Goshen Supervisors approve conditional use for Peirce Middle School additions

Board of Supervisors Conditional Use Hearing · Mon, October 19, 2026

Summary prepared by WCBN from the meeting recording

WCBN uses AI to assist with certain tasks in preparing these summaries. Recaps may contain errors. Always check against the official source linked within each summary. See an error? Email hello@westchesterbythenumbers.com

Summary

The West Goshen Board of Supervisors held a conditional use hearing on the West Chester Area School District's plan to add to and renovate Peirce Middle School at 1314 Burke Road. District witnesses said the project would replace three modular classrooms, add a secure entrance and administrative suite, a music suite and a larger kitchen, and would not increase enrollment. They put the total cost at a little over $70 million. The board voted 5-0 to grant conditional use approval without added conditions; the project still needs land development approval.

Meeting Details

Hearing opened on Peirce Middle School application

Watch at 03:24
  • No one spoke during general public comment, and no neighbors asked to be recognized as parties to the hearing.
  • The township solicitor entered the application, notices and plans into the record; the school straddles the West Whiteland line, and the board rules only on the West Goshen portion.
  • The Zoning Hearing Board had already granted variance relief, and the Planning Commission recommended approval 9-0 on October 13.
  • The district's attorney said the additions are meant to bring the building up to current educational standards, not to add students.

Building additions and project schedule

Watch at 10:07
  • The district's capital programs manager said the school has just over 1,000 students and enrollment will not increase.
  • Three modular classrooms in use since about 2019–2020 would be removed and replaced by classroom additions on the south side of the building.
  • The administrative suite would move to a new addition at the front with a secure vestibule, so visitors no longer enter the building before reaching the office.
  • Other work includes a music suite next to the auditorium, a larger kitchen, HVAC improvements and a modified parent drop-off loop.
  • Work would start in summer 2027 and take 38 to 46 months, scheduled around the school year; total cost is a little over $70 million.

Board questions on safety, materials and asbestos

Watch at 19:59
  • A supervisor asked about emergency vehicle access; the district said driveways from public streets will not change, and staff said truck-turning plans were submitted for land development review.
  • The additions will be no taller than the existing building and will use materials similar to the current building.
  • Asked about asbestos, the district said it believes asbestos was removed during the last renovation, but lead paint is likely on some steel and will be tested.

Site layout, setbacks, parking and landscaping

Watch at 25:29
  • The project's civil engineering project manager said lot coverage rises slightly and green space falls slightly, both still within township limits.
  • The rear classroom addition sits within the 100-foot rear setback but no closer to neighbors than the existing building, which is already nonconforming.
  • Some trees behind that addition will be removed and replaced with new plantings; the existing vinyl fence along the neighbors' yards will stay.
  • About 178 parking spaces exist and the same number will remain after restriping; the ordinance requires about 55.
  • No new athletic field lighting is proposed; one parking lot light pole will be moved.

Stormwater management and construction

Watch at 47:13
  • Roof drains from the additions will be piped to a new underground basin beneath the football field on the West Whiteland side, under a new synthetic turf field and track.
  • The engineer said the peak rate of runoff leaving the site will not increase and the project needs an individual state NPDES construction permit.
  • A supervisor asked about soil piles during the long construction period; the engineer said work areas will be fenced and stabilized, and parking will not be used for storage.
  • The closest work to nearby homes would be regrading of an existing gravel lane.

Traffic study

Watch at 57:37
  • The district's traffic engineer counted traffic on May 20 and 21; peak hours were 7:15–8:15 a.m. and 2:15–3:15 p.m.
  • Using the ordinance's required 5% yearly traffic growth for five years, all studied intersections still rated D or better, and no road improvements were needed.
  • He found one reportable crash in five years near the main driveway and more than 60 empty parking spaces during his count.
  • Supervisors asked about students walking to school; he said he did not observe it from his vantage point but the video data could be reviewed, noting the Planning Commission had raised the same question.

Building appearance and entrance security

Watch at 01:12:25
  • The project architect showed renderings: brick matched to the existing building, metal panels, and sloped metal roofs on classroom additions matching current roofs.
  • Supervisors asked why the bollards shown stop where they do and whether any protect the front entrance; the architect said bollards and other security features are still being evaluated with the district.

Decision

Watch at 01:19:28
  • No one from the public commented on the application.
  • Supervisors said security, stormwater and landscaping details will be addressed in land development review and they saw no need for added conditions.
  • Outcome: conditional use approved 5-0 under Section 84-12.G.1 of the zoning ordinance, consistent with the testimony presented; a written decision will follow.

Action Items

  • Township solicitor to issue a written decision following the board's oral approval.
  • The district's land development plans for the West Goshen portion will go to the Planning Commission and Board of Supervisors for review.
  • District targets the start of construction in summer 2027.

Votes at This Meeting

How we record votes: We record votes of governing boards only (borough council, boards of supervisors, the school board and county commissioners), from the meeting recording or the official minutes. When a voice vote has no audible dissent, we list every member present as voting yes; attendance comes from the roll call. Routine procedural motions may be grouped or left out. Votes taken from recordings are marked Provisional until we check them against the official minutes, which are the official record; if the minutes differ, we correct the vote to match. This record covers only meetings WCBN has recapped and is not a complete voting history. See an error? Email hello@westchesterbythenumbers.com

  • 2026-10-19-01

    Conditional use approval for Peirce Middle School additions and renovations

    Passed
    Provisional — from recording

    Zoning

    Yes: Ashley Gagné, Tinamarie Smith, Shaun Walsh, John Hellmann, Nate WolmanNo: —Abstain: —Absent: —

    Voice vote announced as passing 5-0 with no opposition; no roll call in the recording, so all five members are listed as present based on the 5-0 tally. Mover and seconder not clearly identified. Provisional — from the meeting recording; not yet checked against the official minutes.