Summary

The Crebilly Preserve Master Plan Study Committee held its first meeting with the township's consultant team. The consultants described a planning process running from October 2026 to September 2027, with four public meetings, six committee meetings, focus groups and a public survey, ending with a recommendation to the Board of Supervisors. Committee members commented on the draft survey and brainstormed ideas, including stream buffers, multiple parking entrances, trail connections across Route 202, deer management, horses and past environmental contamination. No votes were taken.

Key Discussion

  • [00:04:00] The consultant team, landscape architects working with ecologists from Princeton Hydro and a traffic engineer, introduced the project. The township manager, the parks coordinator and a Board of Supervisors liaison attend the committee. A Chester County representative joined online.
  • [00:10:30] The consultants outlined the process: four public meetings, six committee meetings broadcast live, about 20 interviews with agencies and key people, four focus groups and four pop-up events, from October 2026 to September 2027. The final plan will go to the Board of Supervisors with a recommendation to approve. They said the master plan is not legally binding and is meant to help the township seek funding, with DCNR, which funded the plan, named as a key partner.
  • [00:17:35] The plan will include cost estimates for trails, parking and habitat restoration, maintenance and stewardship needs for township staff, phasing, and funding strategies.
  • [00:19:12] The Princeton Hydro ecologist said a first site visit recorded more than 60 bird species. He described six main fields, three main drainages and four notable wetlands, and said wooded areas have many invasive plants. He said the site could support grassland bird habitat.
  • [00:24:36] The consultants reviewed a draft public survey on where people live, current park use, and what activities and facilities should be considered at the preserve. A committee member asked for a question focused on passive recreation rather than sports, the ability to sort answers by question, and limits on repeat responses. The consultants agreed to add the question and said they can limit repeat responses. Comments are due by October 30, and the survey goes live November 5.
  • [00:33:21] Asked whether proposed activities are allowed under the property's easements and funding restrictions, the consultants said they believe so but have asked DCNR to clarify some terms. They said a restriction worded as "reforested" was clarified by the township to mean revegetated, which can include meadows. They said the most restrictive easement would apply across the whole site.
  • [00:41:28] In brainstorming, a committee member asked that stream corridors be revegetated to protect water quality; the consultants said the covenants require at least a 150-foot stream buffer. Another member asked for at least two parking entrances. The consultants said they will study access from Route 202, Pleasant Grove Road and Street Road (Route 926) with the traffic engineer.
  • [00:46:07] Committee members asked about the Darlington Inn. The consultants said the township has separated it from the preserve and it is not part of the study, but the plan could recommend planting screens along it. A member also asked for screening around the privately owned five-acre commercial parcel off Route 202.
  • [00:53:25] Committee members asked that the plan avoid construction in the area tied to the Battle of Brandywine, and suggested working with the neighboring church on parking. The consultants said the church has agreed to host parking for the October 24 site walk. History and citizen-science focus groups are planned for December 3 and December 10.
  • [00:57:49] Committee members said Phase I and Phase II environmental studies were done by Toll Brothers before the township bought the land. Members said testing found issues in one area, likely arsenic from a former apple orchard, and that there may be an old dump in the northern woods. Township staff said tanks tied to three demolished buildings were removed, and other items listed in those studies are still on site.
  • [01:01:44] The Princeton Hydro ecologist said one wetland in the central drainage has features of possible bog turtle habitat and will need screening. The consultants said deer management will be part of the plan, with options ranging from fencing to a hunting program with the Game Commission to no hunting.
  • [01:07:48] The consultants said the project will need an NPDES stormwater permit. They said they plan to pair stormwater management with stream and wetland restoration, and may help the township meet its MS4 stormwater requirements.
  • [01:12:09] A committee member asked whether horses will be allowed. The consultants said that is a decision for the township and they will check whether the easements allow it. On trail connections, they said they may seek a meeting with PennDOT about a signalized pedestrian crossing of Route 202 at West Pleasant Grove Road.
  • [01:22:14] Public comment: one resident spoke online about Lenape history and artifacts in the area, geese at the pond near the barn, and a proposed historic trail from the Brandywine Battlefield through Thornbury and Crebilly.
  • [01:24:20] The township manager said project materials, agendas and meeting minutes will be posted on the township's existing Crebilly webpage. The consultants said the second public meeting will show initial concepts, a draft plan is expected in May, and the final plan in September 2027. Committee members also raised shade on trails, seasonal timing of field surveys, and a stream restoration project starting downstream on private property between New Street and Lake Road.

Action Items

  • Committee members to send comments on the draft survey to the township manager by Friday, October 30.
  • Public site walk on Saturday, October 24, with parking at the neighboring church.
  • First public meeting and survey launch on November 5.
  • Second committee meeting on November 12.
  • Focus groups on history (December 3) and citizen science (December 10).
  • Consultants to send the site's topographic survey to committee members and to get clarification from DCNR on easement terms.

Votes at This Meeting

How we record votes: We record votes of governing boards only (borough council, boards of supervisors, the school board and county commissioners), from the meeting recording or the official minutes. When a voice vote has no audible dissent, we list every member present as voting yes; attendance comes from the roll call. Routine procedural motions may be grouped or left out. Votes taken from recordings are marked Provisional until we check them against the official minutes, which are the official record; if the minutes differ, we correct the vote to match. This record covers only meetings WCBN has recapped and is not a complete voting history. See an error? Email hello@westchesterbythenumbers.com

No recorded votes for this meeting.

← Back to all recaps