Westtown Crebilly Preserve Committee: trail concepts, parking access, easement limits
Crebilly Preserve Master Plan Study Committee · Thu, November 12, 2026
Summary prepared by WCBN from the meeting recording
WCBN uses AI to assist with certain tasks in preparing these summaries. Recaps may contain errors. Always check against the official source linked within each summary. See an error? Email hello@westchesterbythenumbers.com
Summary
At its second meeting, the Crebilly Preserve Master Plan Study Committee heard the consultant team summarize the November 5 public meeting and its site analysis of water, slopes, soils, history, plants and wildlife. A traffic engineer identified four possible driveway locations for small parking lots, on West Pleasant Grove Road, Route 202 and Route 926. The consultants showed three early trail concepts of about 3.5 to 4 miles each. No votes were taken. The next committee meeting is January 14, with a public meeting on alternative concepts planned for February.
Key Discussion
- [00:02:00] The consultants said the committee meets again January 14. A history focus group is set for December 3 and a citizen science focus group for December 10. They asked committee members to suggest people to invite, especially people who know local history.
- [00:03:40] The consultants summarized input from the November 5 public meeting. Walking trails were the most requested amenity. The site is expected to be open dawn to dusk with no lighting, and the township still needs to set a dog policy. They said the easements require parking on the site, which will be limited, do not allow income-generating agriculture (so the current hayfield use cannot continue), and require 75 percent of the site to be revegetated. They said timber harvesting is likely in conflict with the easements.
- [00:08:10] The public survey has been live since November 5 and had 52 responses. The consultants asked the township and committee to share it.
- [00:08:45] The consultants reviewed site analysis: streams, wetlands and the 100-year flood area; about 100 feet of elevation difference across the site; mostly gentle slopes, with steeper areas near the creeks and along Street Road; and well-drained soils. The project ecologist found over 50 bird species and over 100 plant species on a first visit. The consultants said deer and beech leaf disease are challenges for planting and the existing tree canopy.
- [00:17:51] A traffic engineer visited the site with the consultants. One road frontage was ruled out because of poor sight lines and a steep bank. Four possible access points were identified: two on West Pleasant Grove Road (one opposite Dunvegan Road), one on Route 202 and one on Route 926 at the site of a demolished house. Parking lots would likely hold 20 cars or fewer. Routes 202 and 926 are PennDOT roads and would need a Highway Occupancy Permit. The Route 202 entrance would be right-in, right-out and would likely need acceleration and deceleration lanes, built at township cost. A committee member asked that lots be designed so they can be expanded.
- [00:26:19] The consultants showed three early trail concepts, each about 3.5 to 4 miles, built as connected loops with a minimum 150-foot buffer on each side of the creeks. They said the plans will change once the ecologist's habitat recommendations are added. Committee members asked about trails in the 100-year floodplain and about reusing existing farm roads. The consultants said trails in these small floodplains are common, and that some of the concepts already use the old farm roads.
- [00:37:32] On accessibility, the consultants said not every trail must be ADA accessible. Accessible trails need stone dust or asphalt. Stone dust can erode on steeper grades, and one participant said Chester County paves trails with slopes over about 2.5 percent. The consultants said the trails will likely need a stormwater permit and stormwater management. They said the township could count work at the preserve toward its MS4 stormwater permit requirements.
- [00:44:50] A committee member asked for trail elevation profiles. The consultants said they would prepare cross sections once a preferred direction is chosen. A committee member suggested small accessible loops near Pleasant Grove Road and Street Road could help decide which parking area to build first.
- [00:58:56] Asked how to give feedback on the trail concepts, the consultants said comments can be emailed to the consulting team. They said they will bring revised options to the committee on January 14, present about three alternative concepts to the public in February, and present a preliminary plan in March or April.
- [01:03:46] A committee member asked for a full list of restrictions in the deed restrictions and grant agreements, with the consultants' reading of each. The consultants agreed and said they hope to send it before the January meeting. They said one funder had told the township that a reforestation requirement means revegetation, and that grant funders want to review the plan as it develops. A committee member said such interpretations should be documented in writing.
- [01:11:41] A committee member asked whether the site's streams are waters of the United States, which would add federal permitting. The consultants said they believe the streams are intermittent and not federal waters, and will check with the ecologist.
Action Items
- History focus group on December 3; citizen science focus group on December 10.
- Committee members to suggest people to invite to the history focus group.
- The traffic engineer will submit a letter report on site access points.
- The consultants will send the committee a list of easement and grant restrictions, with their interpretations, before the January meeting.
- The consultants will check with the ecologist on whether the streams are waters of the United States.
- Next committee meeting January 14, with revised trail concepts; public meeting on alternative concepts planned for February; preliminary plan in March or April.
- Comments on the trail concepts can be emailed to the consulting team; the public survey remains open.
Votes at This Meeting
How we record votes: We record votes of governing boards only (borough council, boards of supervisors, the school board and county commissioners), from the meeting recording or the official minutes. When a voice vote has no audible dissent, we list every member present as voting yes; attendance comes from the roll call. Routine procedural motions may be grouped or left out. Votes taken from recordings are marked Provisional until we check them against the official minutes, which are the official record; if the minutes differ, we correct the vote to match. This record covers only meetings WCBN has recapped and is not a complete voting history. See an error? Email hello@westchesterbythenumbers.com
No recorded votes for this meeting.